Monthly Archives: September 2017

Arbitration Award Ruling That, Because of Cultural Differences, a Local Afghan Subcontractor Is Not Bound by the F.A.R. Provisions Incorporated Into the Subcontracts Is Vacated as Contrary to the Subcontract Terms

Aspic Eng’g & Constr. Co. v. ECC Centcom Constructors, LLC, No. 17-cv-00224-YGR, 2017 U.S. Dist. LEXIS 111767, at *10-12 (N.D. Cal. July 18, 2017) This matter came before the Court on a motion to vacate a final arbitration award (the … Continue reading

Posted in Arbitration, Uncategorized | Tagged , , ,

When Surety Bond Incorporates the Subcontract by Reference, Is the Subcontract’s Arbitration Clause Also Incorporated? Federal Court in South Carolina Says Yes; Federal Court in Kansas Says No — In Two Matters Involving the Same Parties

Developers Sur. & Indem. Co. v. Carothers Constr., Inc., 2017 U.S. Dist. LEXIS 111021 (D.S.C. July 18, 2017); Developers Sur. & Indem. Co. v. Carothers Constr., Inc., 2017 U.S. Dist. LEXIS 135948 (D. Kan. Aug. 24, 2017) Two recent decisions … Continue reading

Posted in Arbitration, Flow Down, Performance Bond, Uncategorized | Tagged , , , , , , , ,

Federal District Court in South Dakota Compels Arbitration Despite Defendant’s Failure to First Submit the Dispute to the Project Engineer as Required by the Disputes Clause

Dlorah, Inc. v. KLE Constr., LLC, No. CIV. 16-5102-JLV, 2017 U.S. Dist. LEXIS 11043 (D.S.D. July 17, 2017) Plaintiff, Dlorah, Inc. (“Dlorah”), filed suit against defendant, KLE Construction, LLC (“KLE”), in connection with an agreement for KLE to perform construction … Continue reading

Posted in Arbitration, Uncategorized | Tagged , , , , , ,

Sharply-Divided Washington Supreme Court Holds That Sureties, Like Insurers, Must Pay Attorney Fees to Prevailing Parties When They Wrongfully Deny Coverage

King Cnty. v. Vinci Constr. Grands Projets/Parsons RCI/ Frontier-Kemper, JV, No. 92744-8, 2017 Wash. LEXIS 743 (July 6, 2017). King County contracted with three construction firms (collectively, “VPFK”) to construct a tunnel.  The contract required substantial completion by November 14, … Continue reading

Posted in Performance Bond, Uncategorized | Tagged , , , , , , , , , ,