Pennsylvania Appellate Court Affirms Homeowner’s Recovery Against Developer on Tort Claims, Despite Contract and Challenges Based on Gist of the Action Doctrine, Economic Loss Rule, and Statute of Limitations

Dolan v. Hurd Millwork Co., No. 2951 EDA 2015, 2019 BL 229344 (Pa. Super. Ct. June 21, 2019)

gazzolaj_thumb
John J. Gazzola

This cases arises out of defective windows installed in a residential construction project. In 1999, Leo J. Dolan purchased a custom home from Bentley Homes, Ltd. and its affiliates (“Bentley Homes”).  Hurd Millwork Company, Inc. provided many of the home’s windows.   Dolan almost immediately observed issues in the home’s construction, including air and water leaks around the windows.   Bentley Homes, however, led him to believe the issues had been fixed.

Continue reading “Pennsylvania Appellate Court Affirms Homeowner’s Recovery Against Developer on Tort Claims, Despite Contract and Challenges Based on Gist of the Action Doctrine, Economic Loss Rule, and Statute of Limitations”

Georgia Court of Appeals Affirms Superior Court’s Confirmation of Arbitration Award, Finding That Arbitrator Did Not Manifestly Disregard Law Governing the “Modified Total Cost” Approach to Damages

Gainesville Mech., Inc. v. Air Data, Inc., No. A19A0518., 2019 BL 229069 (Ga. Ct. App. June 19, 2019)

cuozzom_thumb
Michelle J. Cuozzo

The First Division of the Georgia Court of Appeals affirmed a superior court’s decision to confirm an arbitration award against Appellant Gainesville Mechanical, Inc. (“Gainesville”) because Gainesville failed to show that the arbitrator manifestly disregarded the law governing the “modified total cost” approach to damages.

Continue reading “Georgia Court of Appeals Affirms Superior Court’s Confirmation of Arbitration Award, Finding That Arbitrator Did Not Manifestly Disregard Law Governing the “Modified Total Cost” Approach to Damages”

Georgia’s Supreme Court Re-Affirms The Acceptance Doctrine

Thomaston Acquisition, LLC v. Piedmont Construction Group, Inc., No. S19Q0249, 2019 BL 202176 (Ga. June 03, 2019)

deroor_thumb.jpg
Ryan R. Deroo

 

The acceptance doctrine represents the principle that an independent contractor is not liable for damages occurring after the contractor has completed its work and the work is turned over to and accepted by the owner, provided that the defect was readily observable on reasonable inspection and was not inherently dangerous. Continue reading “Georgia’s Supreme Court Re-Affirms The Acceptance Doctrine”