Federal Court in Pennsylvania Analyzes Which Types of Damage are Barred by Contractual Waiver of Consequential Damages

Jay Jala, LLC v. DDG Construction, Inc., No. 15-3948, 2016 US Dist. LEXIS 150969 (E.D. Pa. Nov. 1, 2016) Jay Jala, LLC was the owner of a motel construction project in Allentown, Pennsylvania. DDG Construction, Inc. was the contractor.  The … Continue reading

Posted in Breach of Contract, Uncategorized | Tagged , , , , ,

Tennessee Federal District Court Holds That Contractor May Pursue Both Breach of Contract Action in Federal Court and Lien Enforcement Action In State Court – Abstention Not Required

Summit Contracting Grp., Inc. v. Ashland Heights, LP,  2016 U.S. Dist. LEXIS 60662 (M.D. Tenn. May 6, 2016) Ashland Heights, LP (“Owner”) contracted with Summit Contracting Group, Inc. (“Contractor”) to construct an assisted living facility in Tennessee.  After completing the … Continue reading

Posted in Breach of Contract, Liens

Court of Federal Claims Rules Contracting Officer’s Failure to Exercise Independent Business Judgment Renders Partial Termination for Convenience an Abuse of Discretion and Breach, but Holds Subsequent Termination for Cause of Remainder of Contract to Be Appropriate

Securiforce Int’l America, LLC v. United States, 125 Fed. Cl. 749 (March 21, 2016) Plaintiff Securiforce International America, LLC (“Securiforce”) was awarded a contract by the Defense Logistics Agency Energy (“DLA Energy” or the “agency”) to deliver diesel fuel and … Continue reading

Posted in Breach of Contract, Termination, Termination for Convenience

Fifth Circuit Considers Allocation of Risk of Defective Plans and Specifications in Reversing $1.29 Million Judgment Entered in Favor of Contractor

Dallas/Fort Worth International Airport Board v. INET Airport Systems, Inc., et al., 2016 U.S. App. LEXIS 6646, 819 F.3d 245 (5th Cir. Apr. 12, 2016)  This action arose out of a construction project in terminal E of the Dallas/Fort Worth … Continue reading

Posted in Breach of Contract, Defective Specifications

Texas District Court Rejects Rail Contractor’s Delay and Prompt Payment Claims and Awards Owner More Than $3 Million

Balfour Beatty Rail, Inc. v. The Kansas City Southern Railway Company, 2016 U.S. Dist. LEXIS 39086 (N.D. Tex., March 25, 2016) The contractor contracted with owner to install 65 miles of railroad track, for a price of $12,206,666.  The owner … Continue reading

Posted in Breach of Contract, Delay, Differing Site Conditions, Extra Work, Payment dispute, Unjust Enrichment