Does a No-Damage-for-Delay Clause Also Preclude Acceleration Damages?

gropmant_thumb
Ted R. Gropman
fanc_thumb
Christine Z. Fan

This article was originally published on December 3, 2019 on ConsensusDocs. It is reprinted here with permission.

Construction contracts often include a “no damage for delay” clause that denies a contractor the right to recover delay-related costs and limits the contractor’s remedy to an extension of time for noncontractor-caused delays to a project’s completion date. Depending on the nature of the delay and the jurisdiction where the project is located, the contractual prohibition against delay damages may well be enforceable. This article will explore whether an enforceable no-damage-for-delay clause is also a bar to recovery of “acceleration” damages, i.e., the costs incurred by the contractor in its attempt to overcome delays to the project’s completion date.

Continue reading “Does a No-Damage-for-Delay Clause Also Preclude Acceleration Damages?”

Owner Did Not Waive Right to Damages by Terminating Design Contract for Convenience

Chinese Hosp. Ass’n v. Jacobs Eng’g Grp., Inc., 2019 BL 330340, 2 (N.D. Cal. Sept. 03, 2019)

fanc_thumb
Christine Z. Fan

This case arises out of the alleged breach of contract and defective design for the construction of a new hospital in San Francisco.  During construction, property owner and plaintiff Chinese Hospital Association (“Chinese Hospital”) became aware of alleged defects involving the designs provided by its subcontractor, architect-defendant Jacobs Engineering Group, Inc. (“Jacobs”).  Chinese Hospital terminated its contract with Jacobs for convenience mid-construction.

Continue reading “Owner Did Not Waive Right to Damages by Terminating Design Contract for Convenience”

Maryland Federal Court Upholds Contractual Indemnity Clause and Awards Judgment Interest and Attorneys Fees in Masonry Suit

Skanska USA Building, Inc. v. J.D. Long Masonry, Inc., No. 1:16-cv-00933, 2019 BL 336852, (D. Md. Sept. 9, 2019)

finizioa_thumb
Anthony V. Finizio

On September 9, 2019, a Maryland federal court awarded Skanska USA Building, Inc. (“Skanska”) compensatory damages, pre- and post-judgment interest, and litigation expenses including attorney and expert fees in its suit against subcontractor J.D. Long Masonry, Inc. (“Long”) for defective masonry work at a Johns Hopkins University research facility.

Continue reading “Maryland Federal Court Upholds Contractual Indemnity Clause and Awards Judgment Interest and Attorneys Fees in Masonry Suit”