Category Archives: Performance Bond

Colorado Court of Appeals Finds Contractor Satisfied Conditions Precedent Under Performance Bond

Whiting-Turner Contracting Co. v Guar. Co. of N. Am. USA, 2019 BL 97923 (Colo. App. Mar. 21, 2019). Danielle J. Volpe This construction dispute involved rights and obligations under a performance bond supplied for an office building construction project in … Continue reading

Posted in Breach of Contract, Performance Bond, Subcontract | Tagged , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , ,

Federal Circuit, Citing the Christian Doctrine, Holds That Performance and Payment Bonds Are Required for All Construction Contracts, Even When the Bonding Requirement Is Not Expressly Stated in the Contract

K-Con, Inc. v. Sec’y of the Army, 2018 U.S. App. LEXIS 31196 (Fed. Cir., November 5, 2018) In September 2013 K-Con, Inc. (“K-Con”) entered into two contracts with the government to supply and construct pre-engineered metal buildings for a laundry … Continue reading

Posted in Performance Bond | Tagged , , ,

When Surety Bond Incorporates the Subcontract by Reference, Is the Subcontract’s Arbitration Clause Also Incorporated? Federal Court in South Carolina Says Yes; Federal Court in Kansas Says No — In Two Matters Involving the Same Parties

Developers Sur. & Indem. Co. v. Carothers Constr., Inc., 2017 U.S. Dist. LEXIS 111021 (D.S.C. July 18, 2017); Developers Sur. & Indem. Co. v. Carothers Constr., Inc., 2017 U.S. Dist. LEXIS 135948 (D. Kan. Aug. 24, 2017) Two recent decisions … Continue reading

Posted in Arbitration, Flow Down, Performance Bond, Uncategorized | Tagged , , , , , , , ,

Sharply-Divided Washington Supreme Court Holds That Sureties, Like Insurers, Must Pay Attorney Fees to Prevailing Parties When They Wrongfully Deny Coverage

King Cnty. v. Vinci Constr. Grands Projets/Parsons RCI/ Frontier-Kemper, JV, No. 92744-8, 2017 Wash. LEXIS 743 (July 6, 2017). King County contracted with three construction firms (collectively, “VPFK”) to construct a tunnel.  The contract required substantial completion by November 14, … Continue reading

Posted in Performance Bond, Uncategorized | Tagged , , , , , , , , , ,

Eleventh Circuit Affirms Decision Under Florida Law Barring Contractor’s Performance Bond Claim for Failure to Comply With Notice Provisions in the Bond and in the Subcontract

Int’l Fidelity Ins. Co. v. Americaribe-Moriarty JV, 2017 U.S. App. LEXIS 3628 (11th Cir. Feb. 28, 2017) Americaribe-Moriarty Joint Venture (“Americaribe”) entered into a subcontract with Certified Pool Mechanics I, Inc. (“CPM”) for construction of a pool in a mixed-use … Continue reading

Posted in Performance Bond, Uncategorized | Tagged , , , ,