District Court in Utah Grants Summary Judgment for Contractor Against Insurance Subrogation Claim Based on Contractual Waiver Provision and Statute of Limitations

Aquatherm, LLC v. CentiMark Corp, 2019 BL 13240 (D. Utah Apr. 12, 2019)

conradj_thumb
John H. Conrad

Stag II Lindon LLC and Stag Industrial Inc. (collectively “Stag”) owned a building in Lindon, Utah.  Stag contracted with CentiMark Corp. (“CentiMark”) to perform work on the building’s roof.  CentiMark’s work required it to manipulate, move, and reinstall existing heating cables on the roof.  Shortly after completion of the work, in March of 2014, a fire occurred on the roof which was traced to the location of heat tape, which CentiMark had removed and replaced.

Continue reading “District Court in Utah Grants Summary Judgment for Contractor Against Insurance Subrogation Claim Based on Contractual Waiver Provision and Statute of Limitations”

Western District of Virginia Confronts Several Legal Issues That Frequently Impact Multi-Party Construction Disputes – Economic Loss, Damage to Other Property, Third Party Beneficiary Status, Warranties, Subrogation, and Third-Party Joinder

Allstate Insurance Company v. Structures Design/Build, LLC, 2016 U.S. Dist. LEXIS 34349 (WD VA March 17, 2016)

This construction dispute case arises from a failed pipe connector that caused water damage to a facility and insured personal property, which Hillel at Virginia Tech, Inc. (“Hillel”) owned in Blacksburg, Virginia. Hillel contracted Structures Design/Build, LLC (“Structures”) to design and construct the facility. Structures, in turn, subcontracted PJ Little Plumbing, Inc. (“PJ”) for plumbing and mechanical installation. PJ purchased the failed pipe connector from CMC Supply, Inc. (“CMC”). Allstate Insurance Company (“Allstate”) insured Hillel for the damage to the facility and the personal property.

As Hillel’s subrogee, Allstate filed a complaint against Structures and PJ. Allstate sued Structures for various state law claims. It sued PJ for negligence and breach of express and implied warranties. PJ filed a third-party complaint to join CMC on a breach of implied warranty theory. PJ and CMC moved to dismiss the claims against them. Continue reading “Western District of Virginia Confronts Several Legal Issues That Frequently Impact Multi-Party Construction Disputes – Economic Loss, Damage to Other Property, Third Party Beneficiary Status, Warranties, Subrogation, and Third-Party Joinder”

Federal Court in Maryland Denies Summary Judgment, Holding That Subcontract Provision Placing Responsibility for Property Damage on Subcontractor Would Likely Trump Prime Contract Waiver of Subrogation Incorporated by Reference

Turner Constr. Co. v. BFPE Int’l, Inc., No. JKB-15-368, 2016 U.S. Dist. LEXIS 39161 (D. Md. Mar. 25, 2016)

The University of Maryland Medical Center (“UMMC”) entered into a contract (the “Prime Contract”) with Turner Construction Company (“Turner”), pursuant to which Turner agreed to renovate UMMC’s hospital offices.  Turner then entered into a subcontract (the “Subcontract”) with BFPE International, Inc. (“BFPE”), pursuant to which BFPE agreed to perform work associated with the fire protection system, including demolishing sprinkler piping and coordinating sprinkler outages to accommodate the renovations.

The Prime Contract included a waiver of subrogation, under which UMMC and Turner waived all rights against each other and any subcontractors for damages covered by property insurance, even if the subcontractor would otherwise have a duty to indemnify.[i]  The Subcontract incorporated the Prime Contract by reference and included flow down provisions, but the Subcontract also stated that if any provision “irreconcilably conflicts” with a provision of the Prime Contract, “the provision imposing the greater duty or obligation on [BFPE] shall govern.”  The Subcontract included an assumption of liability, under which BFPE assumed liability for all property damage in connection with its work and agreed to indemnify Turner from any claims that result.[ii]  This assumption of liability seemed inconsistent with the waiver of subrogation in the Prime Contract. Continue reading “Federal Court in Maryland Denies Summary Judgment, Holding That Subcontract Provision Placing Responsibility for Property Damage on Subcontractor Would Likely Trump Prime Contract Waiver of Subrogation Incorporated by Reference”