District Court in Utah Grants Summary Judgment for Contractor Against Insurance Subrogation Claim Based on Contractual Waiver Provision and Statute of Limitations

Aquatherm, LLC v. CentiMark Corp, 2019 BL 13240 (D. Utah Apr. 12, 2019)

conradj_thumb
John H. Conrad

Stag II Lindon LLC and Stag Industrial Inc. (collectively “Stag”) owned a building in Lindon, Utah.  Stag contracted with CentiMark Corp. (“CentiMark”) to perform work on the building’s roof.  CentiMark’s work required it to manipulate, move, and reinstall existing heating cables on the roof.  Shortly after completion of the work, in March of 2014, a fire occurred on the roof which was traced to the location of heat tape, which CentiMark had removed and replaced.

Continue reading “District Court in Utah Grants Summary Judgment for Contractor Against Insurance Subrogation Claim Based on Contractual Waiver Provision and Statute of Limitations”

A Contractor That Intentionally and Materially Breaches Its Contract Is Not Precluded From Recovery Under Quantum Meruit; Massachusetts Supreme Court Overrules Century-Old Precedent Strictly Barring Such Relief

G4S Tech. LLC v. Mass. Tech. Park Corp., 2018 Mass. Lexis 357 (June 13, 2018)

A state development agency (the “Agency”), received state and federal funding to build a 1,200-mile fiber optic network.  It contracted with G4S Technology LLC (“G4S”) for the project under a $45.5 million design-build agreement.  As a result of project delays – the cause of which the parties disputed – G4S achieved final completion of the work more than one year after the contractual deadline.  Shortly after completion, the Agency issued a notice of withholding, claiming a right to withhold $4 million from G4S to compensate the Agency for delays and expenses incurred as a result of G4S’s alleged failures to perform.

G4S sued the Agency in Massachusetts Superior Court, asserting claims for breach of contract and quantum meruit.  It sought release of the contract balance plus an equitable adjustment of the contract price and deadlines.  In discovery, the Agency learned that G4S had repeatedly submitted inaccurate progress payment applications during the project, which falsely represented that G4S had timely paid its subcontractors.  The Agency cited this evidence in support of a motion for summary judgment, arguing that G4S’s conduct barred its right to recover money owed to it under the contract and under a theory of quantum meruit.  The Superior Court granted the motion, and G4S appealed. Continue reading “A Contractor That Intentionally and Materially Breaches Its Contract Is Not Precluded From Recovery Under Quantum Meruit; Massachusetts Supreme Court Overrules Century-Old Precedent Strictly Barring Such Relief”

Ohio Court of Appeals Rules That Architect’s Authority Does Not Extend to Advancing Payments to Subcontractors, and Architect’s Liability Does Not Extend to Guaranteeing Subcontractors’ Work

Manley Architecture Grp., LLC, v. Santanello, 2018 Ohio App. LEXIS 2372 (June 7, 2018)

Dr. Steven A. Santanello (“Santanello”) contracted with Manley Architecture Group, LLC (“MAG”) to design and manage the construction of a large home, riding barn, pond, tennis court and outdoor pool.  Santanello acted as his own general contractor.

During construction, problems arose with the barn roof, and Santanello stopped paying MAG’s and his subcontractors’ invoices.   MAG advanced $55,557.68 to Santanello’s subcontractors to induce them to complete the project.  MAG later filed a breach of contract action against Santanello seeking to recover these advances.

Santanello filed a counterclaim for breach of contract, alleging that MAG breached its obligation to properly manage the construction of the barn, ultimately necessitating the replacement of the roof.  After a bench trial, the trial court found that both parties had breached the contract.  The parties cross-appealed. Continue reading “Ohio Court of Appeals Rules That Architect’s Authority Does Not Extend to Advancing Payments to Subcontractors, and Architect’s Liability Does Not Extend to Guaranteeing Subcontractors’ Work”