Category Archives: Uncategorized

Bankruptcy Court Holds That “Economic Waste” Doctrine, as Adopted in Wisconsin, Prevented Owner From Recovering Costs to Repair Defectively Designed Digester and Awards No Damages, Even Though the Digester Was Not Designed to the Applicable Code

WTE-S&S AG Enters., LLC v. GHD, Inc., 2017 Bankr. LEXIS 2343 (Bankr. N. D. Ill. August 18, 2017)  This breach of contract dispute arises out of a contract to design and build a cow-manure digester on a farm in Wisconsin.  … Continue reading

Posted in Economic Waste, Uncategorized | Tagged , , , , , , , , ,

Federal Court Holds That Under Louisiana Law, Actual Notice of Cause of Delay Satisfies Contractual Notice Requirement Despite Failure to Strictly Comply With the Notice Provision

Parkcrest Builders, LLC v. Hous. Auth. of New Orleans, 2017 U.S. Dist. LEXIS 125012 (E.D. La. August 8, 2017) The Housing Authority of New Orleans (“the Authority”) contracted with Parkcrest Builders, LLC (“Parkcrest”) to construct a public housing project.  The … Continue reading

Posted in Notice, Uncategorized | Tagged , , , , , , ,

Arbitration Award Ruling That, Because of Cultural Differences, a Local Afghan Subcontractor Is Not Bound by the F.A.R. Provisions Incorporated Into the Subcontracts Is Vacated as Contrary to the Subcontract Terms

Aspic Eng’g & Constr. Co. v. ECC Centcom Constructors, LLC, No. 17-cv-00224-YGR, 2017 U.S. Dist. LEXIS 111767, at *10-12 (N.D. Cal. July 18, 2017) This matter came before the Court on a motion to vacate a final arbitration award (the … Continue reading

Posted in Arbitration, Uncategorized | Tagged , , ,

When Surety Bond Incorporates the Subcontract by Reference, Is the Subcontract’s Arbitration Clause Also Incorporated? Federal Court in South Carolina Says Yes; Federal Court in Kansas Says No — In Two Matters Involving the Same Parties

Developers Sur. & Indem. Co. v. Carothers Constr., Inc., 2017 U.S. Dist. LEXIS 111021 (D.S.C. July 18, 2017); Developers Sur. & Indem. Co. v. Carothers Constr., Inc., 2017 U.S. Dist. LEXIS 135948 (D. Kan. Aug. 24, 2017) Two recent decisions … Continue reading

Posted in Arbitration, Flow Down, Performance Bond, Uncategorized | Tagged , , , , , , , ,

Federal District Court in South Dakota Compels Arbitration Despite Defendant’s Failure to First Submit the Dispute to the Project Engineer as Required by the Disputes Clause

Dlorah, Inc. v. KLE Constr., LLC, No. CIV. 16-5102-JLV, 2017 U.S. Dist. LEXIS 11043 (D.S.D. July 17, 2017) Plaintiff, Dlorah, Inc. (“Dlorah”), filed suit against defendant, KLE Construction, LLC (“KLE”), in connection with an agreement for KLE to perform construction … Continue reading

Posted in Arbitration, Uncategorized | Tagged , , , , , ,