U.S. for Use and Benefit of Greenmoor, Inc. v. Travelers Casualty and Surety Co.
2009 U.S. Dist. LEXIS 113153 (W.D. PA 12/04/2009)
The Court held that a properly terminated subcontractor was nevertheless entitled to payment for contract work and extras performed prior to termination, less certain offsets for contractor’s damages. Subcontractor was also entitled to interest at 1% per month under a prompt payment statute, but because it was properly terminated was not entitled to lost profit on the terminated portion of the subcontract.
Continue Reading US District Court for Western District of PA Holds Contractor Owes Properly Terminated Subcontractor Payment for Work Performed Prior to Termination Plus CASPA Interest