BEGL Construction Company, Inc. et al. v. Los Angeles Unified School District and Star Insurance Com
154 Cal.App.4th 970; 2007 Cal.App. LEXIS 1432 (2007)
In August 2000, the Los Angeles Unified School District (the “District”) entered into a public works construction contract with BEGL Construction Company, Inc. (“BEGL”) for a seismic retrofit of the Science Building at its Los Angles Center for Enriched Studies (“LACES”) and demolition and reconstruction of the LACES West Arcade. Because the project was a public work, BEGL was required to post a performance bond and a payment bond. Subsequently, after BEGL commenced performing work, the West Arcade was removed from the scope of the contract.Continue Reading California Court Upholds Recovery of Lost Profits Due to Impaired Bonding Capacity