Dugan Construction Company, Inc. v. New Jersey Turnpike Authority
941 A.2d 622 (N.J. Super. Ct. App. Div. 2008)
The Superior Court of New Jersey, Appellate Division, recently had to decide whether a contractor was entitled to the contractual per unit price for the removal of substantial quantities of groundwater where the estimated quantity in the bid documents was grossly understated and contractor failed to bring the error to the public entities’ attention. Analyzing the case utilizing principles of patent ambiguity and reformation, the Court held that the mistake in the bid documents warranted reformation of the contract and the contractor was only permitted to recoup the actual value of the work performed.
Continue Reading New Jersey Superior Court Appellate Division Reforms Unit Price in Public Contract Where Contractor Knew Estimated Quantities Were Grossly Understated and Had Unbalanced Its Bid To Take Advantage of Error