California Supreme Court Clarifies That “Right to Repair Act” is Exclusive Remedy for Both Economic Loss and Property Damage Arising From Construction Defects

McMillin Albany LLC v. Superior Court, No. S229762, 2018 Cal. LEXIS 211 (Jan. 18, 2018)

Several homeowners (“Plaintiffs”) brought suit against developer/general contractor McMillin Albany LLC (“McMillin”) for alleged defective construction of new homes.  Plaintiffs alleged the defects caused property damage and economic loss in the form of repair costs and reduced property values, and asserted common law claims for negligence, strict product liability, breach of contract, and breach of warranty, and a statutory claim for violation of the construction standards outlined in the Right to Repair Act (Civ. Code §§ 895–945.5, the “Act”).  The Act defines standards for the construction of individual dwellings; governs various builder obligations, including provision of warranties; creates a prelitigation dispute resolution process; and describes mandatory procedures for lawsuits under the Act.  McMillin sought a stay of proceedings so that the parties could proceed through the Act’s prelitigation dispute process, which includes notice to the builder of defects and an opportunity to cure.  Plaintiffs refused to stipulate to the stay and instead, dismissed their statutory claim.  McMillin then sought a court-ordered stay which Plaintiffs contested, arguing that their suit now omitted any claim under the Act, and therefore, was not subject to its procedures. Continue reading “California Supreme Court Clarifies That “Right to Repair Act” is Exclusive Remedy for Both Economic Loss and Property Damage Arising From Construction Defects”

Kentucky Appellate Court Holds That a Contractor May Pursue Claim of Negligent Misrepresentation Against Architect Despite Lack of Contract, the Economic Loss Rule, and Project Waivers

D.W. Wilburn, Inc. v. K. Norman Berry Assocs., No. 2015-CA-001254-MR, 2016 Ky. App. Lexis 206 (Ky. Ct. App. Dec. 22, 2016)

This case arose out of a construction project in which the Oldham County Board of Education (the “Board”) was the owner, K. Norman Berry Associates (“KNBA”) was the architect and D.W. Wilburn (“Wilburn”) was the general contractor. The Board’s contract with Wilburn provided that: (i) change orders must be signed by the architect, contractor, and owner; (ii) claims for additional time, money or delay damages must be submitted within twenty-one days of the event giving rise to the claim; (iii) change orders resolved all claims for time and money relating to the scope of the change order, and (iv) the contractor’s acceptance of final payment waived its claims, except those identified in writing as unsettled at the time of final application for payment.  Pursuant to the contract, the parties executed twenty-one change orders and Wilburn submitted a final payment application and closeout form.

Later, Wilburn was sued by one of its subcontractors for delay to the project. Wilburn then sued KNBA in a third party complaint asserting that KNBA was liable for the delay as a result of its defective plans and specifications.  The trial court granted KNBA summary judgment, dismissing Wilburn’s claim for lack of contractual privity.  Wilburn appealed, and the Court of Appeals reversed. Continue reading “Kentucky Appellate Court Holds That a Contractor May Pursue Claim of Negligent Misrepresentation Against Architect Despite Lack of Contract, the Economic Loss Rule, and Project Waivers”