First Gen. Constr. Corp., Inc. v. Kasco Constr. Co., Inc.
2011 U.S. Dist. LEXIS 55349 (E.D. Pa. May 24, 2011)
Kasco was the general contractor for a shopping center expansion. Kasco subcontracted the concrete work to First General. The subcontract included a term requiring First General to submit, upon request, releases of liens, with its payment applications. The Contract also required written approval of extra work, timely written notice of claims within ten days of their occurrence, and the submission of written backup information.Continue Reading U.S. District Court In Pennsylvania Holds Extra Work Claims Barred By Releases Submitted With Periodic Payment Requests And By Noncompliance With Requirements For Submission Of Documentation For Extra Work Claims