Current Builders of Florida, Inc. v. First Sealord Surety, Inc.
2008 Fla. App. LEXIS 4698 (April 2, 2008)
The Court of Appeals of Florida held that a jury finding that a contractor which terminated a subcontractor failed to provide notice in accordance with the terms of a performance bond was sustainable, given that the contractor did not tender the remaining contract balance to the surety or give it an opportunity to provide for the completion of the work. Accordingly, the surety’s obligations under the bond were not triggered.
Continue Reading Florida Court Holds That Contractor’s Failure To Provide Notice Of Default In Accordance With Terms Of Performance Bond Discharged Surety From Its Obligations