Excel Construction, Inc. v. HKM Engineering, Inc.
2010 WY 34 (Wyo. Mar. 23, 2010)
The Supreme Court of Wyoming recently reexamined its prior ruling barring a contractor’s assertion of negligence claims against design professionals economic loss rule.
The case pertained to a construction project for the replacement and improvement of water and sewer lines in the Town of Lovell, Wyoming. The Town of Lovell entered into an engineering services agreement with HKM Engineering, Inc. The Town also entered into a construction agreement with Excel Construction, Inc. No contract existed between HKM and Excel.Continue Reading Supreme Court of Wyoming Declines to Modify Precedent Barring Claims by Contractor Against Design Professional Under the Economic Loss Rule