Tag Archives: Miller Act

Subcontract Provision Requiring Subcontractor to Pass Through its Claims Does Not Prevent the Subcontractor From Suing to Recover Against Miller Act Bond

Pinnacle Crushing & Constr. LLC v. Hartford Fire Ins. Co., 2018 U.S. Dist. LEXIS 67965 (W.D. Wa. Apr. 23, 2018) The Army Corps of Engineers (the “Corps”), as owner, and Cherokee General Corporation (“CGC”), as prime contractor, entered into a … Continue reading

Posted in Miller Act, Pass-Through, Waiver | Tagged , , , , , ,

Federal Court in Mississippi Holds That Although Projects Were Constructed With Federal Funds, They Were Not “A Public Work of the Federal Government” and Therefore the Court Had No Jurisdiction Over a Subcontractor’s Claim Under the Miller Act, Where the United States Was Not a Contracting Party and the Projects Were Not Constructed on Federal Property

United States ex rel. Metro Mech., Inc. v. Triangle Constr. Co.,  2018 U.S. Dist. LEXIS 1487 (S.D. Miss. Jan. 4, 2018) Triangle Construction Company, Inc. (“Triangle”) contracted with Mississippi Portfolio Partners III, LP (“Mississippi Partners”) to serve as the prime … Continue reading

Posted in Miller Act, Payment bond | Tagged , , , , ,

Federal Court in Oklahoma Rules that Bond Issued on a Sovereign Tribal Construction Project is Not a Miller Act Bond Even Though it Stated it was Issued Pursuant to the Act and Named The United States As Obligee

United States ex rel. J.A. Manning Constr. Co. v. Bronze Oak, 2017 U.S. Dist. LEXIS 6054 (N.D. Okla. Jan. 17, 2017)  In May 2014 the Cherokee Nation issued a bid notice for bridge and roadway construction in Mayes County, Oklahoma … Continue reading

Posted in Government Contract, Miller Act, Uncategorized | Tagged , , ,

U.S. District Court in Maryland Holds Work Performed After Termination Does Not Delay Commencement of One-Year Miller Act Statute of Limitations

United States ex rel. Tymatt Indus. v. Allen & Shariff Constr. Servs. 2013 U.S. Dist. LEXIS 114015 (D. Md. Aug. 13, 2013) This action arose out of a subcontractor’s Miller Act claim for unpaid contract balances on a federal construction … Continue reading

Posted in Miller Act | Tagged , , ,

U.S. District Court in Maryland Holds One-Year Statute of Limitations Under Miller Act Did Not Commence Until After Required Testing Performed by Subcontractor

United States of America ex rel D&M General Contracting, Inc v. Arch Ins. Co. 2013 U.S. Dist. LEXIS 111260 (D. Md. Aug. 5, 2013) This action arose out of subcontractor’s claim for increased costs allegedly incurred as a result of … Continue reading

Posted in Miller Act | Tagged , , ,