Tag Archives: Miller Act

Federal Circuit, Citing the Christian Doctrine, Holds That Performance and Payment Bonds Are Required for All Construction Contracts, Even When the Bonding Requirement Is Not Expressly Stated in the Contract

K-Con, Inc. v. Sec’y of the Army, 2018 U.S. App. LEXIS 31196 (Fed. Cir., November 5, 2018) In September 2013 K-Con, Inc. (“K-Con”) entered into two contracts with the government to supply and construct pre-engineered metal buildings for a laundry … Continue reading

Posted in Performance Bond | Tagged , , ,

Claimant Is Not Required to Conduct an Investigation Into the Veracity of the Representation to Prove Justifiable Reliance When Asserting a Fraudulent Inducement Claim Under the Miller Act

Fisk Elec. Co. v. DQSI, L.L.C., 2018 U.S. App. LEXIS 17914 (5th Cir., June 29, 2018)  DQSI, L.L.C., (“DQSI”) a general contractor, was hired by the Army Corps of Engineers (“Corps”) for a pump station construction project.  Western Surety Company … Continue reading

Posted in fraud | Tagged , , , , , ,

Subcontract Provision Requiring Subcontractor to Pass Through its Claims Does Not Prevent the Subcontractor From Suing to Recover Against Miller Act Bond

Pinnacle Crushing & Constr. LLC v. Hartford Fire Ins. Co., 2018 U.S. Dist. LEXIS 67965 (W.D. Wa. Apr. 23, 2018) The Army Corps of Engineers (the “Corps”), as owner, and Cherokee General Corporation (“CGC”), as prime contractor, entered into a … Continue reading

Posted in Miller Act, Pass-Through, Waiver | Tagged , , , , , ,

Federal Court in Mississippi Holds That Although Projects Were Constructed With Federal Funds, They Were Not “A Public Work of the Federal Government” and Therefore the Court Had No Jurisdiction Over a Subcontractor’s Claim Under the Miller Act, Where the United States Was Not a Contracting Party and the Projects Were Not Constructed on Federal Property

United States ex rel. Metro Mech., Inc. v. Triangle Constr. Co.,  2018 U.S. Dist. LEXIS 1487 (S.D. Miss. Jan. 4, 2018) Triangle Construction Company, Inc. (“Triangle”) contracted with Mississippi Portfolio Partners III, LP (“Mississippi Partners”) to serve as the prime … Continue reading

Posted in Miller Act, Payment bond | Tagged , , , , ,

Federal Court in Oklahoma Rules that Bond Issued on a Sovereign Tribal Construction Project is Not a Miller Act Bond Even Though it Stated it was Issued Pursuant to the Act and Named The United States As Obligee

United States ex rel. J.A. Manning Constr. Co. v. Bronze Oak, 2017 U.S. Dist. LEXIS 6054 (N.D. Okla. Jan. 17, 2017)  In May 2014 the Cherokee Nation issued a bid notice for bridge and roadway construction in Mayes County, Oklahoma … Continue reading

Posted in Government Contract, Miller Act, Uncategorized | Tagged , , ,