About Constructlaw.com
Constructlaw® is an update and discussion of recent trends in construction law and construction litigation. It is edited by Robert E. Heideck, partner in Pepper Hamilton LLP's Construction Law Practice Group. Additional contributors are listed on the Contributors page. For more information about Pepper's Construction Practice Group, click here.Subscribe via RSS
Subscribe by E-Mail
Blogroll
- ABA Construction Litigation Committee, Section of Litigation
- ABA Forum Committee on the Construction Industry
- American Arbitration Association
- American Institute of Architects
- American Society of Civil Engineers
- Associated Builders and Contractors
- Associated General Contractors
- Construction Superconference
- Construction Users Roundtable
Recent Past Posts
- April 2018 (3)
- March 2018 (5)
- February 2018 (4)
Tag Archives: Parkcrest Builders
Federal Court Holds That Under Louisiana Law, Actual Notice of Cause of Delay Satisfies Contractual Notice Requirement Despite Failure to Strictly Comply With the Notice Provision
Parkcrest Builders, LLC v. Hous. Auth. of New Orleans, 2017 U.S. Dist. LEXIS 125012 (E.D. La. August 8, 2017) The Housing Authority of New Orleans (“the Authority”) contracted with Parkcrest Builders, LLC (“Parkcrest”) to construct a public housing project. The … Continue reading