Federal Court Holds That it Lacks Subject Matter Jurisdiction to Review VA’s Decision to Begin Debarment Proceedings Since That Decision Is Not a Final Agency Action

Hope v. Dep’t of Veterans Affairs, 2018 U.S. Dist. LEXIS 28479 (E.D. Ark. Feb. 22, 2018)

This matter involved a motion for temporary restraining order and preliminary injunction (the “Motion”) filed by Richard Alan Hope (“Hope”) and his HVAC company, Powers of Arkansas (“Powers”), asking the District Court to prohibit the Department of Veterans Affairs (“VA”) from continuing debarment proceedings against them.  In 2012, Federal agents began investigating Hope for fraudulently presenting DAV Construction Company, Inc. as a legitimate service-disabled, veteran-owned small business in order to obtain government construction contracts.  Hope was indicted in 2016 for conspiracy to defraud, among other things.  The VA thereafter suspended Hope and Powers from government contracting based on the indictment.  The indictment was ultimately dismissed after the Court declared a mistrial.  In January of 2018, the VA lifted the suspensions, but issued notices of proposed debarment to Hope and Powers.  While debarment proceedings are pending, a contractor may not be awarded government contracts.

The Court first analyzed jurisdiction.  Absent waiver, sovereign immunity shields the VA from suit.  However, the Administrative Procedure Act (“APA”) waives sovereign immunity to allow judicial review of final agency actions.  The Court held that it lacked jurisdiction here because there was no final agency decision as to the proposed debarment.  Indeed, the VA has established procedures for debarment decisions and the proposal for debarment is only the first step.  The Court found that because the VA’s decision-making process had only just begun, and there had been no final agency action, the APA did not authorize the Court to review the merits of the proposed debarment at this time.  Continue reading

Posted in Debarment | Tagged , , , , , , , ,

Contractor Who Failed to Challenge Arbitration Award Within Statutory Three Month Period Cannot Resurrect the Challenge as an “Affirmative Defense” to a Later Action for Confirmation

St. George Fire Prot. Dist. No. 2 v. J. Reed Constructors, Inc. 2018, La. App. LEXIS 262 (February 20, 2018)

J. Reed Constructors, Inc. (“J. Reed”) and St. George Fire Protection District No. 2 (“St. George”) entered into two construction contracts under which disputes were subject to binding arbitration. A dispute arose in which J. Reed contested St. George’s assessment of liquidated damages and claims for breach of warranty. The matter was submitted to arbitration and the arbitrator awarded St. George $58,865.00.

St. George petitioned the trial court to confirm the arbitration award, pointing out that the three month deadline for the parties to request that the award be vacated, modified, or corrected had lapsed.  J. Reed answered the petition by objecting to the confirmation of $41,660.00 for architect and attorney fees.  J. Reed acknowledged that it did not file a motion to modify within three months of the award, as required by the Louisiana Binding Arbitration Law (the “Act”), but argued that it was not prohibited from raising its objection as an affirmative defense in its answer to the petition.

The trial court rejected J. Reed’s argument and confirmed the award.  The Court of Appeals affirmed, holding that J. Reed’s right to challenge the award had been waived and could not be revived by characterizing the challenge as an affirmative defense to the petition to confirm.  Continue reading

Posted in Arbitration | Tagged , , ,

Divided New York Court of Appeals Holds That a Third Party Cannot Sue for Breach of Contract Absent Express Language Naming Them as an Intended Beneficiary and That Claims for Breach of Contract and Professional Negligence Against an Architect Cannot Both Be Maintained When the Allegations Supporting Both Claims Are Nearly Identical

Dormitory Auth. of the State of NY v. Samson Constr. Co., 2018 N.Y. Lexis 218 (February 15, 2018)

The Dormitory Authority of the State of New York (“DASNY”) undertook, as project manager, to construct a facility for the Office of the Chief Medical Examiner of the City of New York (the “City”) as a forensic biology laboratory (the “Project”).  DASNY retained Perkins Eastman Architects, P.C. (“Perkins”) as architect for the Project, and Samson Construction Co. (“Samson”) as the foundation contractor.

Complications during the construction of the foundation resulted in 18 months of delays due to the adjacent building settling eight inches, damages to the adjacent sidewalks, utilities and emergency repairs.  DASNY and the City filed suit against Samson, and later joined Perkins, asserting claims against Perkins for breach of contract and negligence.

Perkins moved for summary judgment to dismiss the City’s claims, and to dismiss DASNY’s negligence claim as duplicative of its breach of contract claim.  The trial court dismissed the City’s breach of contract claim; holding that the City was not an intended third-party beneficiary of the contract between DASNY and Perkins (the “Contract”), and allowed both DASNY’s breach of contract and negligence claims to proceed, holding that the claims were not duplicative of each another. Continue reading

Posted in Negligence, Third Party Beneficiary | Tagged , , ,

Can a Nonsignatory to an Arbitration Agreement Compel Arbitration by Estoppel? North Carolina Court of Appeals Says Yes — But Not in This Particular Case

Smith Jamison Constr. v. Apac-Atlantic, Inc., 2018 N.C. App. LEXIS 132 (N.C. Ct. App. Feb. 6, 2018)

General contractor APAC-Atlantic (“APAC”) hired Smith Jamison Construction (“Jamison”) as a subcontractor to perform concrete work on a highway project.  The APAC-Jamison subcontract included an agreement that the parties would arbitrate all claims arising out of or relating to their subcontract.  Jamison alleged that APAC later sought to have Jamison further subcontract the concrete work to Yates Construction Company (“Yates”).  According to Jamison, APAC terminated the subcontract when Jamison refused to subcontract with Yates.

Jamison sued APAC and Yates in state court, alleging that APAC had breached its subcontract with Jamison and that Yates had committed fraudulent misrepresentation, tortious interference, civil conspiracy, and violations of the North Carolina unfair and deceptive trade practices statute.  Both APAC and Yates sought to compel arbitration of the claims Jamison asserted against them.  The court ordered arbitration of Jamison’s claims against APAC based on the arbitration agreement in their subcontract.  The court denied Yates’s attempt to compel arbitration.  Like APAC, Yates also based its argument on the arbitration agreement in the subcontract between Jamison and APAC – a contract to which Yates was not a party.  Yates appealed. Continue reading

Posted in Arbitration | Tagged , , ,

Supreme Court of Vermont Holds That Contractor Waived its Right to Challenge the Validity of Arbitration Agreement by Actively Participating in the Arbitration for Six Months Before Raising an Objection

Adams v. Barr, 2018 VT 12, 2018 Vt. LEXIS 10 (VT 2018)

On February 24, 2016, Barr Law Group (“Barr”) filed a demand for arbitration with the American Arbitration Association to recover $40,000 in unpaid legal fees from its client, Adams Construction VT, LLC (“Adams”).  Adams responded by filing an answer and counterclaim, seeking to recover $97,000 in damages from Barr.  Thereafter, Adams and Barr each actively participated in the arbitration, including arbitrator selection, preliminary conferences, extensive discovery and motion practice over a period of more than five months.  At the request of Adams, the matter was set for a three day hearing.

In October of 2016, just one week before the three day hearing was set to begin, Adams filed an objection and motion to dismiss the arbitration, arguing that the arbitration clause in its fee agreement with Barr was unenforceable.  Specifically, Adams argued that Barr, as Adams’ counsel, owed a fiduciary duty and ethical obligations that required it to disclose to Adams the rights it would forego by signing the agreement.  According to Adams, Barr had failed to explain the legal implication of the arbitration clause and failed to advise Adams to obtain independent counsel before signing the agreement.  However, Adams’ objection and motion to dismiss was the first time it had raised any objection to the arbitration proceedings.   Continue reading

Posted in Arbitration, Waiver | Tagged , , , , ,