COVID-19 and the Construction Industry: Important Considerations (For Information Purposes Only Not Intended as Legal Advice)

Jamey B. Collidge

COVID-19 has created a severe disruption to the construction industry. Certain jurisdictions, including Boston, San Francisco and Pennsylvania, have placed restrictions on construction projects deemed “nonessential” and require waivers for certain projects to continue. Owners, contractors, suppliers and others may currently have more questions than answers. This article addresses some important concerns, and provides links to additional resources that more specifically address these concerns. Continue reading “COVID-19 and the Construction Industry: Important Considerations (For Information Purposes Only Not Intended as Legal Advice)”

Continuous Cessation of Labor on Construction Projects Can Trigger Statutory Remedy Deadlines

eatonl_thumb
Luke Nicholas Eaton

State and local governments throughout the country continue to issue orders in response to the novel coronavirus (COVID-19) outbreak. Many states have ordered the shutdown of all businesses, with various exceptions such as businesses that are “essential” and/or “life-sustaining.” Each jurisdiction has provided a list and/or guidance on what kinds of businesses must close and what can remain open. Pepper Hamilton continues to monitor these orders and update its “COVID-19 – State Business Impact Tracker” map, an interactive tool that shows shutdown orders by state. The Business Impact Tracker can be accessed at https://covid19.pepperlaw.com/. Continue reading “Continuous Cessation of Labor on Construction Projects Can Trigger Statutory Remedy Deadlines”

Does a No-Damage-for-Delay Clause Also Preclude Acceleration Damages?

gropmant_thumb
Ted R. Gropman
fanc_thumb
Christine Z. Fan

This article was originally published on December 3, 2019 on ConsensusDocs. It is reprinted here with permission.

Construction contracts often include a “no damage for delay” clause that denies a contractor the right to recover delay-related costs and limits the contractor’s remedy to an extension of time for noncontractor-caused delays to a project’s completion date. Depending on the nature of the delay and the jurisdiction where the project is located, the contractual prohibition against delay damages may well be enforceable. This article will explore whether an enforceable no-damage-for-delay clause is also a bar to recovery of “acceleration” damages, i.e., the costs incurred by the contractor in its attempt to overcome delays to the project’s completion date.

Continue reading “Does a No-Damage-for-Delay Clause Also Preclude Acceleration Damages?”