January 2017

Jay Jala, LLC v. DDG Construction, Inc., No. 15-3948, 2016 US Dist. LEXIS 150969 (E.D. Pa. Nov. 1, 2016)

Jay Jala, LLC was the owner of a motel construction project in Allentown, Pennsylvania. DDG Construction, Inc. was the contractor.  The project was delayed during construction and, four months after the specified completion date, DDG abandoned the project.  Jay Jala terminated DDG for default, completed the project, and initiated this action.

The contract provided that the parties “waive Claims against each other for consequential damages arising out of or relating to this Contract.” During litigation, DDG stipulated that it breached the contract but moved for partial summary judgment, arguing that Jay Jala’s damages were consequential, and thus waived.

U.S. Pipelining LLC v. Johnson Controls, Inc., No. 16-00132 HG-RLP, 2016 U.S. Dist. LEXIS 150767 (D. Haw. Oct. 31, 2016)

This action arose out of the renovation of a condominium complex on Maui (Project). Johnson Controls, Inc. (JCI) was the general contractor and U.S. Pipelining LLC (USP) was a subcontractor. While the parties disputed who was ultimately responsible for obtaining a license for the work, the Subcontract included a provision that required USP to “obtain[] all licenses and permits required for the prosecution of the Work.” Nonetheless, USP performed its work without obtaining a license from the State of Hawaii. During the Project, a dispute arose between the parties. USP filed a complaint alleging various claims against JCI and others, seeking payment for the additional work it allegedly performed.

Chapter 444 of the Hawaii Revised Statutes (the “Statute”) requires contractors to obtain a license before performing any renovation work on real property.