Contractor’s Third Party Beneficiary Claim Dismissed Against Designer Where Designer’s Contract with Owner Lacked Clear Intent to Benefit the Contractor

Arco Ingenierosm, S.A. v. CDM Int’l Inc., Civil Action No. 18-12348-PBS, 2019 BL 100779 (D. Mass. Mar. 22, 2019) Luke Nicholas Eaton In November 2009, Tropical Storm Ida hit El Salvador, causing flooding, landslides, and the destruction of homes, roads, … Continue reading

Posted in Breach of Contract, Design/Build | Tagged , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , ,

Connecticut Superior Court Affirms Judgment for Contractor on Claim for Extra Work, Holds Substantial Compliance Satisfies Notice Requirement and Approves Damages Calculated on Variants of the Total Cost Method and Eichleay Formula

Paragon Constr. Co. v. Dep’t of Pub. Works 2013 Conn. Super LEXIS 789 (Conn. Super. Ct. 2013) The Connecticut Department of Public Works and the Connecticut Department of Corrections (collectively “the State”) solicited bids for the renovation of a correctional … Continue reading

Posted in Breach of Contract | Tagged , , ,