Federal Court in Hawaii Holds that an Unlicensed Subcontractor May Pursue Contract Claims Against Contractor Notwithstanding Statute Precluding Unlicensed Contractors from Recovering in a Civil Action

U.S. Pipelining LLC v. Johnson Controls, Inc., No. 16-00132 HG-RLP, 2016 U.S. Dist. LEXIS 150767 (D. Haw. Oct. 31, 2016)

This action arose out of the renovation of a condominium complex on Maui (Project). Johnson Controls, Inc. (JCI) was the general contractor and U.S. Pipelining LLC (USP) was a subcontractor. While the parties disputed who was ultimately responsible for obtaining a license for the work, the Subcontract included a provision that required USP to “obtain[] all licenses and permits required for the prosecution of the Work.” Nonetheless, USP performed its work without obtaining a license from the State of Hawaii. During the Project, a dispute arose between the parties. USP filed a complaint alleging various claims against JCI and others, seeking payment for the additional work it allegedly performed.

Chapter 444 of the Hawaii Revised Statutes (the “Statute”) requires contractors to obtain a license before performing any renovation work on real property. Continue reading “Federal Court in Hawaii Holds that an Unlicensed Subcontractor May Pursue Contract Claims Against Contractor Notwithstanding Statute Precluding Unlicensed Contractors from Recovering in a Civil Action”