Travelers Casualty and Surety Company of America

Fid. & Deposit Co. of Md. v. T

ravelers Cas. & Sur. Co. of Am., 2018 U.S. Dist. LEXIS 162265 (D. Nev., September 21, 2018)
Clark County School District (“CCSD”) hired Big Town Mechanical (“Big Town”) as general contractor to perform HVAC upgrades at five schools.  Big Town in turn hired F.A.S.T. Systems (“FAST”) to complete low-voltage work at the schools.  Big Town obtained performance bonds from Travelers Casualty and Surety Company of America (“Travelers”) and FAST obtained performance bonds from Fidelity & Deposit Company of Maryland (“F&D”).

Following FAST’s default on its subcontracts, F&D opted to complete FAST’s work and hired a substitute subcontractor, Perini.  In May 2012, Perini notified Big Town that it had “substantially completed” all of FAST’s work.  After Big Town refused payment, F&D filed suit against Big Town and Travelers in early 2013.  In May of 2013, CCSD rejected Big Town’s final payment application, stating that the project was incomplete and claiming there were significant defects in the work.  CCSD then sued Travelers seeking specific performance and liquidated damages for delay.  Travelers eventually settled CCSD’s suit but through its counterclaim sought reimbursement from F&D for its settlement plus costs expended to complete the project.
Continue Reading Concurrent Delay: Surety—Standing in the Shoes of Subcontractor—Is Barred From Asserting Defense of Concurrent Delay Because Subcontractor Failed to Seek a Time Extension as Required by the Subcontracts

Sachse Constr. & Dev. Corp. v. Affirmed Drywall, Corp., 2018 Fla App. Lexis 9998 (July 18, 2018)

Sachse Construction, a Michigan-based general contractor, entered into a subcontract (the “Subcontract”) with Affirmed Drywall Corp. (“Affirmed”), a Florida drywall subcontractor, to perform work on a property in Florida.  The Subcontract provided that all disputes be resolved by mediation and/or arbitration in Southfield, Michigan, or within 20 miles thereof, pursuant to the Construction Industry Rules of the American Arbitration Association and in accordance with Michigan laws.  However, under Section 47.025 of the Florida Statutes, a venue provision in a contract involving a Florida-based contractor or subcontractor, etc., for the improvement of real property located in Florida is considered void as a matter of public policy if it requires that legal action be brought outside of Florida.

Affirmed filed an action in Florida state court alleging claims for breach of contract against Sachse and to recover against a bond naming Sachse and the surety on the bond.  Sachse moved to dismiss or to compel arbitration in Michigan in accordance with the dispute resolution provision in the Subcontract.  Sachse argued that the Subcontract involved interstate commerce, so the Federal Arbitration Act (the “FAA”) governed the Subcontract and preempted inconsistent state law.  Sachse claimed that Section 47.025 did not void the provision in the Subcontract mandating that disputes be resolved by arbitration in Michigan because of the FAA’s liberal policy favoring arbitration agreements.  The trial court disagreed, denied Sachse’s motion and ordered Sachse to answer the complaint.  Sachse appealed.
Continue Reading Federal Arbitration Act Preempts Florida State Statute Which Prohibits Out-of-State Resolution of Construction Claims Involving Florida Real Property